The employee was exiting an excavator, climbing down the tracks to the step. He slipped from the step and fell to the ground landing on his lunch box. There was, according to other employees, some mud on the step. The employee was angry in leaving his equipment, due to the fact that he was to quit operating one piece and start operating another.
Marett Mine Coal
Marett Mine tiene $24K en multas propuestas de MSHA y $0 pendientes en 5 expedientes impugnados, ademas del muestreo de salud y el registro completo de incidentes.
Seguir esta mina
Avísenme cuando se presente un nuevo incidente de la MSHA en Marett Mine.
- Muertes
- 0
- Incidentes totales
- 2
- Años en registro
- 2009–2011
- Último incidente
- Mar 2011
ⓘ
Esta tasa son las citaciones registradas divididas entre las horas de inspección de la MSHA, por cada 100 horas. Refleja el esfuerzo de inspección, no el tamaño de la mina ni la producción.Marett Mine tiene $24K en multas propuestas de MSHA y $0 pendientes en 5 expedientes impugnados.
ⓘ
Las diferencias entre las multas propuestas y las pagadas reflejan tanto acuerdos y reducciones en conferencia como montos aun adeudados. Pendiente es el saldo que se debe actualmente.El muestreo de MSHA en Marett Mine muestra un polvo respirable de carbon promedio de 0.28 mg/m3 (100% en cumplimiento) en 88 muestras.
ⓘ
Una muestra es una medicion de cumplimiento en un momento dado, no un historial de exposicion individual. Estas cifras describen registros de muestreo de MSHA y no establecen causalidad ni dosis personal.ⓘ
Las cifras de polvo respirable de carbon y silice corresponden a instalaciones de carbon. El cumplimiento del polvo se mide frente a la norma actual de 1.5 mg/m3; se incluyen muestras anteriores a la norma de 2014, por lo que las tasas de cumplimiento son una senal historica aproximada.ⓘ
Citaciones por millón de horas-empleado reportadas. Las tasas comienzan en el año 2000, cuando inician los datos trimestrales de empleo de la MSHA; los incidentes anteriores se cuentan pero no pueden ajustarse por tasa. Los trimestres con menos de 100,000 horas reportadas se muestran en gris: muy pocas horas para una tasa estable.| Trimestre | Horas trabajadas | Citaciones | S&S | Por 1M hrs |
|---|---|---|---|---|
| 2012 Q3 | 1,436 | 1 | 0 | 696.4 |
| 2012 Q2 | 0 | 1 | 0 | |
| 2012 Q1 | 4,879 | 0 | 0 | 0.0 |
| 2011 Q4 | 8,940 | 2 | 1 | 223.7 |
| 2011 Q3 | 13,448 | 0 | 0 | 0.0 |
| 2011 Q2 | 14,999 | 4 | 2 | 266.7 |
| 2011 Q1 | 14,789 | 0 | 0 | 0.0 |
| 2010 Q4 | 12,176 | 6 | 2 | 492.8 |
Mostrar 38 trimestres anteriores Ocultar trimestres anteriores
| Trimestre | Horas trabajadas | Citaciones | S&S | Por 1M hrs |
|---|---|---|---|---|
| 2010 Q3 | 9,934 | 0 | 0 | 0.0 |
| 2010 Q2 | 7,603 | 8 | 5 | 1052.2 |
| 2010 Q1 | 6,453 | 0 | 0 | 0.0 |
| 2009 Q4 | 16,726 | 1 | 1 | 59.8 |
| 2009 Q3 | 1,982 | 1 | 0 | 504.5 |
| 2009 Q2 | 3,693 | 0 | 0 | 0.0 |
| 2009 Q1 | 8,682 | 4 | 2 | 460.7 |
| 2008 Q4 | 13,199 | 0 | 0 | 0.0 |
| 2008 Q3 | 13,296 | 7 | 5 | 526.5 |
| 2008 Q2 | 6,941 | 1 | 1 | 144.1 |
| 2008 Q1 | 0 | 0 | 0 | |
| 2007 Q4 | 5,161 | 0 | 0 | 0.0 |
| 2007 Q3 | 4,808 | 0 | 0 | 0.0 |
| 2007 Q2 | 5,125 | 0 | 0 | 0.0 |
| 2007 Q1 | 4,318 | 0 | 0 | 0.0 |
| 2006 Q4 | 4,423 | 1 | 1 | 226.1 |
| 2006 Q3 | 5,491 | 0 | 0 | 0.0 |
| 2006 Q2 | 5,887 | 3 | 1 | 509.6 |
| 2006 Q1 | 5,251 | 0 | 0 | 0.0 |
| 2005 Q4 | 4,167 | 0 | 0 | 0.0 |
| 2005 Q3 | 4,350 | 0 | 0 | 0.0 |
| 2005 Q2 | 3,437 | 1 | 0 | 291.0 |
| 2005 Q1 | 4,561 | 0 | 0 | 0.0 |
| 2004 Q4 | 7,779 | 0 | 0 | 0.0 |
| 2004 Q3 | 6,656 | 0 | 0 | 0.0 |
| 2004 Q2 | 3,900 | 0 | 0 | 0.0 |
| 2004 Q1 | 3,328 | 1 | 0 | 300.5 |
| 2002 Q3 | 198 | 0 | 0 | 0.0 |
| 2002 Q2 | 1,916 | 2 | 0 | 1043.8 |
| 2002 Q1 | 1,828 | 0 | 0 | 0.0 |
| 2001 Q4 | 1,120 | 0 | 0 | 0.0 |
| 2001 Q3 | 1,032 | 0 | 0 | 0.0 |
| 2001 Q2 | 1,234 | 0 | 0 | 0.0 |
| 2001 Q1 | 1,163 | 0 | 0 | 0.0 |
| 2000 Q4 | 1,163 | 0 | 0 | 0.0 |
| 2000 Q3 | 1,237 | 0 | 0 | 0.0 |
| 2000 Q2 | 1,250 | 3 | 2 | 2400.0 |
| 2000 Q1 | 1,374 | 0 | 0 | 0.0 |
Incidentes reportables
2 en archivo2011 · 1 incidente
2009 · 1 incidente
The employee was working on the outside of a hopper that became jammed with material. He was using a pry bar to clear material from the hopper (were it discharges onto a belt). The employee had the bar resting on his shoulder using his legs for power. Later in the day a pain developed and continued to get worse. He went to the local E.R. & was diagnosed with tendonitis/strain.
The full compliance file on Marett Mine
A dated report covering the 26-year penalty trail, line-item violation pattern, contest and docket posture, rate-normalized peer benchmark, and full fatality history. Delivered as a PDF with the underlying data as CSV.