Mining Incidents

CRIVITZ GRAVEL, INC. Metal/Non-Metal

Controlled by John P Bartkowski III
Crivitz, WI, Marinette County, WI  ·  Abandoned
MSHA Mine ID: 4702819

CRIVITZ GRAVEL, INC. has $495 in proposed MSHA penalties and $0 outstanding across 0 contested dockets, plus health sampling and the full incident record.

Watch this mine

Email me when a new MSHA incident is filed at CRIVITZ GRAVEL, INC..

Fatalities
0
Total incidents
1
Years on record
2003
Latest incident
Dec 2003
Compliance record
MSHA citations since 2003
7
citations
1
significant & substantial
$495
proposed penalties
$495
paid to date
100% of proposed penalties paid to date, a $0 gap.
Source: MSHA violations data, updated weekly.
Inspection activity
MSHA inspections since 2001
28
inspections on record
139
inspection hours
n/a
citations per 100 inspection hours
This rate is recorded citations divided by MSHA inspection hours, per 100 hours. It reflects inspection effort, not mine size or production.
Rate withheld: 139 inspection hours is too few for a stable rate. A minimum of 1,000 inspection hours is required.
Source: MSHA inspections data, updated weekly.

CRIVITZ GRAVEL, INC. has $495 in proposed MSHA penalties and $0 outstanding across 0 contested dockets.

Penalty disposition
Differences between proposed and paid penalties reflect both settlements and conference reductions and amounts still owed. Outstanding is the balance currently owed.
$495
proposed penalties
$495
current assessed
$495
paid to date
$0
outstanding
7 assessments are final orders; 0 contested dockets.
As of the most recent assessment on 2005-08-24.
Source: MSHA assessed-violations and conference/litigation data, updated weekly.
Quarterly safety rates
Citations per million reported employee-hours. Rates begin in 2000, when MSHA's quarterly employment data starts; earlier incidents are counted but cannot be rate-adjusted. Quarters under 100,000 reported hours are greyed: too few hours for a stable rate.
Citations per million employee-hours, as reported to MSHA
Quarter Hours worked Citations S&S Per 1M hrs
2019 Q2 0 0 0
2019 Q1 0 0 0
2018 Q4 0 0 0
2018 Q3 0 0 0
2018 Q2 0 0 0
2018 Q1 0 0 0
2017 Q4 4 0 0 0.0
2017 Q3 0 0 0
Show 68 earlier quarters
Quarter Hours worked Citations S&S Per 1M hrs
2017 Q2 0 0 0
2017 Q1 0 0 0
2016 Q4 0 0 0
2016 Q3 0 0 0
2016 Q2 1 0 0 0.0
2016 Q1 0 0 0
2015 Q4 0 0 0
2015 Q3 0 0 0
2015 Q2 0 0 0
2015 Q1 0 0 0
2014 Q4 0 0 0
2014 Q3 0 0 0
2014 Q2 0 0 0
2014 Q1 0 0 0
2013 Q4 0 0 0
2013 Q3 0 0 0
2013 Q2 0 0 0
2013 Q1 0 0 0
2012 Q4 30 0 0 0.0
2012 Q3 20 0 0 0.0
2012 Q2 0 0 0
2012 Q1 0 0 0
2011 Q4 10 0 0 0.0
2011 Q3 8 0 0 0.0
2011 Q2 0 0 0
2011 Q1 0 0 0
2010 Q4 10 0 0 0.0
2010 Q3 44 0 0 0.0
2010 Q2 10 0 0 0.0
2010 Q1 0 0 0
2009 Q4 0 0 0
2009 Q3 20 0 0 0.0
2009 Q2 0 0 0
2009 Q1 0 0 0
2008 Q4 0 0 0
2008 Q3 4 0 0 0.0
2008 Q2 0 0 0
2008 Q1 0 0 0
2007 Q4 40 0 0 0.0
2007 Q3 10 0 0 0.0
2007 Q2 0 0 0
2007 Q1 0 0 0
2006 Q4 24 0 0 0.0
2006 Q3 8 0 0 0.0
2006 Q2 24 0 0 0.0
2006 Q1 0 0 0
2005 Q4 40 0 0 0.0
2005 Q3 16 4 1 250000.0
2005 Q2 40 0 0 0.0
2005 Q1 0 0 0
2004 Q4 10 0 0 0.0
2004 Q3 20 0 0 0.0
2004 Q2 72 0 0 0.0
2004 Q1 0 0 0
2003 Q4 35 0 0 0.0
2003 Q3 1 3 0 3000000.0
2002 Q4 0 0 0
2002 Q3 48 0 0 0.0
2002 Q2 30 0 0 0.0
2002 Q1 0 0 0
2001 Q4 80 0 0 0.0
2001 Q3 0 0 0
2001 Q2 0 0 0
2001 Q1 0 0 0
2000 Q4 55 0 0 0.0
2000 Q3 0 0 0
2000 Q2 8 0 0 0.0
2000 Q1 15 0 0 0.0
No fatalities recorded at this mine.

Reportable incidents

1 on file

2003 · 1 incident

December 3, 2003 WI · Metal/Non-Metal

FROST WAS IN THE MATERIAL THAT HAD BEEN CRUSHED THE PREVIOUS DAY. MATERIAL WAS BEING RELOCATED FROM THE DISCHARGE PILE OF THE CRUSHER. THE TOP OF THE PILE WAS FROZEN. IN REMOVING THE LOWER AR EA OF THE DISCHARGE PILE, THE TOP OF THE PILE CAME DOWN AND CRUSHED OUR EE'S ANKLE AND FOOT. AT THE TIME OF INJURY, HE WAS MAINTAINING THE CRUSHER.