EE WAS TRYING TO OPEN DOOR ON LOADER LEADING TO PLACE TO CHECK TRANSMISSION FLUID-THE DOOR WAS STUCK. HE PULLED HARD ON IT AND FELT A TWINGE IN HIS LEFT NECK/SHOULDER AREA. CAME TO WORK THE NE XT DAY AND WAS IN VEY BAD PAIN BY THE END OF THE DAY. CANNOT WORK AT THIS POINT-TOO PAINFUL.
Apache Plant #2 Metal/Non-Metal
R E Glancy Inc
· Surface
Controlled by
Kevin Ford Manne
Tawas,
Iosco County,
MI
·
Intermittent
MSHA Mine ID: 2002402
Apache Plant #2 has $1K in proposed MSHA penalties and $700 outstanding across 0 contested dockets, plus health sampling and the full incident record.
Watch this mine
Email me when a new MSHA incident is filed at Apache Plant #2.
- Fatalities
- 0
- Total incidents
- 1
- Years on record
- 2001
- Latest incident
- Oct 2001
Compliance record
MSHA citations since 2000
6
citations
2
significant & substantial
$1,269
proposed penalties
$569
paid to date
45% of proposed penalties paid to date, a $700 gap.
Source: MSHA violations data, updated weekly.
Inspection activity
MSHA inspections since 2000
16
inspections on record
131
inspection hours
n/a
citations per 100 inspection hours
ⓘ
This rate is recorded citations divided by MSHA inspection hours, per 100 hours. It reflects inspection effort, not mine size or production.Rate withheld: 131 inspection hours is too few for a stable rate. A minimum of 1,000 inspection hours is required.
Source: MSHA inspections data, updated weekly.
Apache Plant #2 has $1K in proposed MSHA penalties and $700 outstanding across 0 contested dockets.
Penalty disposition
ⓘ
Differences between proposed and paid penalties reflect both settlements and conference reductions and amounts still owed. Outstanding is the balance currently owed.$1K
proposed penalties
$1K
current assessed
$569
paid to date
$700
outstanding
4 assessments are final orders; 0 contested dockets.
As of the most recent assessment on 2026-04-29.
Source: MSHA assessed-violations and conference/litigation data, updated weekly.
See also
the operator's enforcement record
Quarterly safety rates
ⓘ
Citations per million reported employee-hours. Rates begin in 2000, when MSHA's quarterly employment data starts; earlier incidents are counted but cannot be rate-adjusted. Quarters under 100,000 reported hours are greyed: too few hours for a stable rate.Citations per million employee-hours, as reported to MSHA
| Quarter | Hours worked | Citations | S&S | Per 1M hrs |
|---|---|---|---|---|
| 2025 Q4 | 1 | 0 | 0 | 0.0 |
| 2025 Q3 | 1 | 0 | 0 | 0.0 |
| 2025 Q2 | 1,980 | 0 | 0 | 0.0 |
| 2025 Q1 | 1 | 0 | 0 | 0.0 |
| 2024 Q4 | 1 | 0 | 0 | 0.0 |
| 2024 Q3 | 1,546 | 0 | 0 | 0.0 |
| 2024 Q2 | 1,009 | 0 | 0 | 0.0 |
| 2011 Q3 | 1 | 0 | 0 | 0.0 |
Show 39 earlier quarters Hide earlier quarters
| Quarter | Hours worked | Citations | S&S | Per 1M hrs |
|---|---|---|---|---|
| 2011 Q2 | 1 | 0 | 0 | 0.0 |
| 2011 Q1 | 1 | 0 | 0 | 0.0 |
| 2010 Q4 | 1 | 0 | 0 | 0.0 |
| 2010 Q3 | 1 | 0 | 0 | 0.0 |
| 2010 Q2 | 1 | 0 | 0 | 0.0 |
| 2010 Q1 | 1 | 0 | 0 | 0.0 |
| 2009 Q4 | 0 | 0 | 0 | |
| 2009 Q3 | 0 | 0 | 0 | |
| 2009 Q2 | 0 | 0 | 0 | |
| 2009 Q1 | 0 | 0 | 0 | |
| 2008 Q4 | 0 | 0 | 0 | |
| 2008 Q3 | 1 | 0 | 0 | 0.0 |
| 2008 Q2 | 0 | 0 | 0 | |
| 2008 Q1 | 1 | 0 | 0 | 0.0 |
| 2007 Q4 | 2 | 0 | 0 | 0.0 |
| 2007 Q3 | 1,427 | 0 | 0 | 0.0 |
| 2007 Q2 | 0 | 0 | 0 | |
| 2007 Q1 | 2 | 0 | 0 | 0.0 |
| 2006 Q4 | 0 | 0 | 0 | |
| 2006 Q3 | 634 | 0 | 0 | 0.0 |
| 2006 Q2 | 1,033 | 0 | 0 | 0.0 |
| 2006 Q1 | 1 | 0 | 0 | 0.0 |
| 2005 Q4 | 0 | 0 | 0 | |
| 2005 Q3 | 1,844 | 1 | 0 | 542.3 |
| 2005 Q2 | 90 | 0 | 0 | 0.0 |
| 2003 Q2 | 1 | 0 | 0 | 0.0 |
| 2003 Q1 | 1 | 0 | 0 | 0.0 |
| 2002 Q4 | 0 | 0 | 0 | |
| 2002 Q3 | 942 | 0 | 0 | 0.0 |
| 2002 Q2 | 3,456 | 0 | 0 | 0.0 |
| 2002 Q1 | 1 | 0 | 0 | 0.0 |
| 2001 Q4 | 2,031 | 0 | 0 | 0.0 |
| 2001 Q3 | 3,124 | 0 | 0 | 0.0 |
| 2001 Q2 | 4,109 | 0 | 0 | 0.0 |
| 2001 Q1 | 57 | 0 | 0 | 0.0 |
| 2000 Q4 | 2,083 | 0 | 0 | 0.0 |
| 2000 Q3 | 5,806 | 0 | 0 | 0.0 |
| 2000 Q2 | 3,223 | 3 | 1 | 930.8 |
| 2000 Q1 | 175 | 0 | 0 | 0.0 |
No fatalities recorded at this mine.
Reportable incidents
1 on file2001 · 1 incident
October 16, 2001
MI · Metal/Non-Metal
bulldozer operator, universal operator, heavy equipment operator, operating engineer
HANDLING OF MATERIALS
R E Glancy Inc · Over-exertion in pulling or pushing objects
For insurers, brokers, and safety consultants
The full compliance file on Apache Plant #2
A dated report covering the 26-year penalty trail, line-item violation pattern, contest and docket posture, rate-normalized peer benchmark, and full fatality history. Delivered as a PDF with the underlying data as CSV.