Mining Incidents

Georgia Stone Spring Hill Quarry Metal/Non-Metal

Masaryktown, Pasco County, FL  ·  Active
MSHA Mine ID: 0801402

Georgia Stone Spring Hill Quarry has $50K in proposed MSHA penalties and $2K outstanding across 1 contested dockets, plus health sampling and the full incident record.

Watch this mine

Email me when a new MSHA incident is filed at Georgia Stone Spring Hill Quarry.

Fatalities
0
Total incidents
2
Years on record
2018–2021
Latest incident
Oct 2021
Compliance record
MSHA citations since 2015
85
citations
34
significant & substantial
$50,095
proposed penalties
$47,604
paid to date
95% of proposed penalties paid to date, a $2,491 gap.
Source: MSHA violations data, updated weekly.
Inspection activity
MSHA inspections since 2015
39
inspections on record
455
inspection hours
n/a
citations per 100 inspection hours
This rate is recorded citations divided by MSHA inspection hours, per 100 hours. It reflects inspection effort, not mine size or production.
Rate withheld: 455 inspection hours is too few for a stable rate. A minimum of 1,000 inspection hours is required.
Source: MSHA inspections data, updated weekly.

Georgia Stone Spring Hill Quarry has $50K in proposed MSHA penalties and $2K outstanding across 1 contested dockets.

Penalty disposition
Differences between proposed and paid penalties reflect both settlements and conference reductions and amounts still owed. Outstanding is the balance currently owed.
$50K
proposed penalties
$49K
current assessed
$48K
paid to date
$2K
outstanding
84 assessments are final orders; 1 contested dockets.
As of the most recent assessment on 2026-02-14.
Source: MSHA assessed-violations and conference/litigation data, updated weekly.
Quarterly safety rates
Citations per million reported employee-hours. Rates begin in 2000, when MSHA's quarterly employment data starts; earlier incidents are counted but cannot be rate-adjusted. Quarters under 100,000 reported hours are greyed: too few hours for a stable rate.
Citations per million employee-hours, as reported to MSHA
Quarter Hours worked Citations S&S Per 1M hrs
2025 Q4 7,082 0 0 0.0
2025 Q3 8,509 1 1 117.5
2025 Q2 9,793 0 0 0.0
2025 Q1 9,384 0 0 0.0
2024 Q4 4,432 1 0 225.6
2024 Q3 4,878 0 0 0.0
2024 Q2 4,790 3 0 626.3
2024 Q1 4,820 0 0 0.0
Show 35 earlier quarters
Quarter Hours worked Citations S&S Per 1M hrs
2023 Q4 5,150 1 0 194.2
2023 Q3 4,790 0 0 0.0
2023 Q2 4,460 3 0 672.6
2023 Q1 4,460 1 0 224.2
2022 Q4 7,050 0 0 0.0
2022 Q3 6,720 1 0 148.8
2022 Q2 6,430 0 0 0.0
2022 Q1 4,800 0 0 0.0
2021 Q4 6,370 10 9 1569.9
2021 Q3 5,760 11 8 1909.7
2021 Q2 5,570 0 0 0.0
2021 Q1 5,115 5 1 977.5
2020 Q4 3,580 0 0 0.0
2020 Q3 421 8 3 19002.4
2020 Q2 365 0 0 0.0
2020 Q1 1,820 3 1 1648.4
2019 Q4 30 0 0 0.0
2019 Q3 10 0 0 0.0
2019 Q2 90 0 0 0.0
2019 Q1 106 0 0 0.0
2018 Q4 264 0 0 0.0
2018 Q3 82 0 0 0.0
2018 Q2 500 2 1 4000.0
2018 Q1 1,608 0 0 0.0
2017 Q4 2,038 2 1 981.4
2017 Q3 2,319 0 0 0.0
2017 Q2 2,982 2 0 670.7
2017 Q1 2,868 0 0 0.0
2016 Q4 3,241 6 1 1851.3
2016 Q3 3,259 2 0 613.7
2016 Q2 3,780 0 0 0.0
2016 Q1 1,980 3 1 1515.2
2015 Q4 1,267 0 0 0.0
2015 Q3 1,437 0 0 0.0
2015 Q2 1,918 7 2 3649.6
No fatalities recorded at this mine.

Reportable incidents

2 on file

2021 · 1 incident

October 15, 2021 FL · Metal/Non-Metal miner, prospector, nec POWERED HAULAGE
Lago Verde Mine, LLC · Caught in, under or between a moving and a stationary object

Employee climbed on belt to clear a clog, EE was not tied off, and EE did not LO/TO. The plant operator started the plant while employee was still on belt. Employee grabbed the drive pully to catch themselves and the belt cut first and second finger. Second finger was repaired in surgery. The first finger was removed from fingernail down during surgery.

2018 · 1 incident

April 26, 2018 FL · Metal/Non-Metal rotary bucket excavator operator MACHINERY
Outlaw Ridge Inc · Struck against a moving object

Site inspection on 4/27/18 showed 3" of slightly loose soil conditions under the left track. The right track had solid ground conditions. The excavator was removed from the lake on 4/28/18. Inspection of the excavator showed the bucket to be 3/4 full of shot rock and curled almost up beneath and between the tracks. It appears the operator undermined self.

For insurers, brokers, and safety consultants

The full compliance file on Georgia Stone Spring Hill Quarry

A dated report covering the 26-year penalty trail, line-item violation pattern, contest and docket posture, rate-normalized peer benchmark, and full fatality history. Delivered as a PDF with the underlying data as CSV.